Project Description

The work involved a complete dilapidation and office fit out, all work was completed within a 5 week period.

Offices were remodelled and upgraded by installing new suspended ceilings and partition walls. Low energy recessed lighting with Datom cabling and points to each office. The office floors were completed with engineered Oak flooring. Noppe rubber flooring was used throughout the other areas.

All washrooms were plastered, retiled and fitted with contemporary sanitary ware. All plumbing works and electrics were commissioned and certificated to meet Landlord requirements.

The completed works were complimented by a pastel colour scheme, giving a real feeling of light and space throughout.